Understanding the Tendering Process: An Overview for SMEs
Understanding the tendering process is essential for small and medium-sized enterprises taking their first steps into public sector contracting. Government contracts offer stable, long-term revenue streams worth billions each year to UK businesses.
At Bid Writer Consultancy, we’ve guided hundreds of SMEs through successful tender submissions. This guide shares practical insights to help you understand how tendering works, what to expect at each stage, and how to position your business for success.
Tendering is a structured procurement method used by organisations to select suppliers through competitive bidding. For public sector bodies, it’s a legal requirement for purchases above certain thresholds, ensuring fair competition and value for money.
The tendering process follows a defined sequence: identification of need, market engagement, formal invitation to tender, submission, evaluation, award, and contract implementation. Each stage involves specific activities and documentation, with strict rules governing communication and timeframes.
For SMEs, tendering represents both opportunity and challenge. The structured nature of the process creates a more level playing field than informal networking-based business development, allowing smaller businesses to compete based on capability rather than existing relationships. However, the administrative demands and compliance requirements can strain limited resources.
Understanding the ‘why’ behind tendering helps navigate the process more effectively. Public bodies must demonstrate fair, transparent use of public funds. Their procurement processes are designed to reduce risk, ensure quality, and deliver value. Your responses must address these core concerns to succeed.
Most public tenders are evaluated using a combination of quality and price criteria. The weighting between these factors varies dramatically – from 100% price-based (lowest cost wins) to heavily quality-focused evaluations where innovative approaches or specialised expertise command premium prices. Knowing the evaluation model is fundamental to developing a competitive strategy.
Public Sector vs Private Sector Tendering: Key Differences
Public and private sector procurement serve different masters and operate under different rules. Understanding these distinctions helps you adapt your approach accordingly.
Public sector tendering follows prescribed regulations, primarily the Public Contracts Regulations 2015 and the newer Procurement Act 2023. These establish mandatory procedures, transparency requirements, and remedies for suppliers who believe they’ve been unfairly treated. Public bodies must advertise opportunities above certain thresholds, provide the same information to all bidders, and evaluate bids using declared criteria.
Communication in public tenders is tightly controlled. Questions must be submitted through formal channels, with responses shared with all bidders. Direct contact with decision-makers outside these channels is typically prohibited. This creates a structured but sometimes frustrating experience compared to private sector sales.
Private sector purchasing varies enormously in formality. Some large companies use processes nearly identical to public procurement, while others rely on more informal approaches driven by relationships and negotiation. Private buyers generally have greater flexibility to change requirements mid-process, negotiate terms with preferred suppliers, or abort the process altogether.
For SMEs, this difference means adapting your engagement strategy. Public tenders demand strict adherence to process, with success hinging on your ability to score well against published criteria. Private procurement may allow more room to influence requirements and build relationships with decision-makers before and during the bidding process.
Timescales also differ significantly. Public tenders typically follow regulated minimum timeframes – usually at least 30 days from advertisement to submission for most procedures. Private purchases can move much faster, sometimes condensing the entire process into days or weeks when necessary.
The Construction Tendering Process: Industry-Specific Requirements
Construction tendering has distinct characteristics reflecting the technical complexity and financial scale of building projects. If you operate in this sector, you’ll encounter industry-specific requirements beyond standard procurement practices.
Most construction tenders begin with extensive pre-qualification. Buyers scrutinise financial standing, safety records, insurance coverage, and technical capability in detail before considering your actual bid. Expect to provide evidence of relevant experience, completed projects, qualifications, and accreditations specific to construction work.
Health and safety receives particular emphasis. You’ll need to demonstrate robust safety management systems, training programmes, risk assessment methodologies, and accident records. Memberships in schemes like Constructionline, CHAS, or SafeContractor often serve as initial filters for participation.
Technical submissions in construction typically include preliminary programmes, method statements, resource allocations, and quality management plans. Larger projects may require BIM capability statements, sustainability assessments, and detailed supply chain management proposals. These elements receive meticulous assessment by technical experts within the evaluation team.
Pricing formats vary from straightforward lump sums to complex bills of quantities requiring detailed cost breakdowns. Tender documentation often includes contractual terms specific to construction, such as JCT or NEC forms, with provisions covering variations, retention, defects periods, and programme management.
The rise of framework agreements has changed construction procurement significantly. Major buyers like local authorities, housing associations, and central government departments often establish multi-year frameworks with approved contractors. Gaining a place on relevant frameworks is increasingly essential for consistent work flow in this sector.
Step-by-Step Guide to the Complete Tender Cycle
Understanding each stage of the tender cycle helps you plan effectively and allocate resources where they matter most.
1. Market Engagement
Market engagement begins before formal tendering starts. Organisations often publish future procurement plans or Planned Procurement Notices (formerly PINs) signalling upcoming opportunities. Some hold supplier engagement events or publish draft specifications for comment. Active participation at this stage can provide valuable insights into buyer priorities and shape requirements in your favour.
2. Selection Stage
Selection stage filters potential bidders based on minimum standards of capability and capacity. This may involve a Pre-Qualification Questionnaire (PQQ), Selection Questionnaire (SQ), or similar screening tool. Questions typically cover company information, financial standing, technical capability, relevant experience, and policies. Public sector buyers increasingly use standardised forms to reduce the administrative burden on suppliers.
3. Invitation to Tender (ITT)
ITT is issued to selected suppliers. This package includes instructions to tenderers, specifications, evaluation criteria, contract terms, response templates, and pricing schedules. Careful analysis of these documents is essential – we’ve seen capable companies fail simply because they misunderstood requirements or evaluation mechanisms.
4. Clarification Period
Clarification period allows suppliers to ask questions about the tender requirements. Questions must be submitted by a specified deadline, with anonymised answers shared with all bidders. Strategic use of clarification questions can highlight ambiguities in the specification or prompt the buyer to reconsider problematic requirements.
5. Submission
Submission involves providing your completed response by the stated deadline. Most tenders now require electronic submission through procurement portals. Formatting, file naming conventions, and technical requirements must be followed precisely – non-compliant submissions risk rejection regardless of content quality.
6. Evaluation
Evaluation is conducted by the buyer’s team using the published methodology. Responses are typically scored by multiple evaluators, with moderation to ensure consistency. This process can take days or weeks depending on the complexity of the tender and number of submissions received.
7. Award Decision
Award decision communicated to all bidders simultaneously. For public contracts, this triggers the standstill period (usually 10 calendar days) during which unsuccessful bidders can request feedback and, if necessary, challenge the decision. Only after this period expires is the contract formally awarded.
8. Mobilisation and Implementation
Mobilisation and implementation follows award, transitioning from bid commitments to operational delivery. The thoroughness of this transition directly impacts contract success – every promise made in your tender becomes a contractual obligation that must be fulfilled.
Timelines in Tendering: What to Expect and How to Plan
“How long will it take?” is among the most common questions SMEs ask about tendering. While timeframes vary depending on procedure type and contract complexity, understanding typical durations helps with resource planning.
From opportunity identification to contract award, the complete cycle for a significant public tender typically spans 3-6 months. This breaks down approximately as:
-
Pre-tender engagement: 1-3 months
-
Selection stage: 3-4 weeks
-
Invitation to tender preparation: 2-4 weeks
-
Tender open period: 2-6 weeks
-
Evaluation: 2-6 weeks
-
Standstill and award: 2 weeks
-
Mobilisation: 2-12 weeks